Logo
STORE REQUISITION SLIP

U.P. Pt. Deen Dayal Upadhyaya Pashu-Chikitsa Vigyan Vishwavidyalaya
Evam Go-Anusandhan Sansthan, Mathura-281001 (UP)

Original Copy

Letter No: Date: 05-05-2026
College: College of Veterinary Science & A. H. Department: Dean Office, COVSc. & A. H.
Nature of Requirement: Non-Recurring Funding Source: University Grant
Note: Each Indent must pertain to only one category.
Project/Scheme Title:
Sanctioned Amount (Enclosed Annexure ): β‚Ή0.00

Purpose & Justification:
The New Committee Room is used for official meetings and discussions involving faculty, officers, and guests. Due to lack of proper cooling, it becomes uncomfortable during summer, affecting productivity and meeting efficiency. Installation of a Split AC is essential to maintain a comfortable environment, ensure smooth conduct of meetings, and protect electronic equipment.


Details of Items:
S.N. Item Description & Catalogue No (if applicable) Specifications Make/Brand(Only in case of RC) Qty Unit Cost (β‚Ή) Approx Cost (β‚Ή)
1 Split Air Conditioner 2 Ton Capacity, 3 Star or Heavy Duty 4.00 70,000.00 280,000.00
2 Voltage Stabilizer 5KVA Double Phase Capacity for 2 Ton AC 4.00 20,000.00 80,000.00
3 AC Installation with Copper Pipe and other Accessories Copper pipe, Insulation, wiring, drainage pipe, stand etc. 4.00 10,000.00 40,000.00
Specifications must be generic and non-proprietary (not brand specific).
Sub Total: β‚Ή400,000.00
GST: β‚Ή72,000.00
Grand Total: β‚Ή472,000.00
AMC Required: No AMC Duration: N/A

Certification:
It is certified that the rates of the above items/services have been verified from different sources and found reasonable.( Enclosed rate reasonability Annexure )

(Indentor Signature)
Date: _____________
(HOD/Officer Signature)
Date: _____________
(Dean/Director Signature)
Date: _____________